A standard home EV charger installation takes around 3 to 6 hours on the day — most installers finish in a morning or afternoon. Jobs that need a consumer unit upgrade, a long cable run or groundworks under a drive can take a full day, occasionally two.
From first enquiry to a working charger, one to three weeks is typical, depending on how quickly you can get a survey (often done from photos), installer availability in your area and whether anything needs sorting with the network operator first.
How long each part of the job takes
| Stage | Typical time | What happens |
|---|---|---|
| Arrival and final checks | 15–30 minutes | Confirm the charger position, cable route and isolation point with you. |
| Running the cable | 1–2 hours | Drilling through the wall, fixing the cable along its route, fitting into the consumer unit. |
| Mounting the charger | 30–60 minutes | Fixing the unit (and any pedestal) and terminating the cable. |
| Protection and load management | 30–60 minutes | Fitting the circuit protection and a current clamp on the meter tails. |
| Testing and commissioning | 30–60 minutes | Electrical tests, connecting to Wi-Fi and the app, a test charge. |
| Handover | 15–30 minutes | Showing you the app and scheduling, and leaving the paperwork. |
What makes an installation take longer
Most of the variation comes from the property, not the charger. Allow extra time for:
- A consumer unit replacement — usually adds two to four hours and a longer power-off. See do I need a new consumer unit?.
- A long or awkward cable run — through several rooms, a loft or a garage. See long cable runs.
- Groundworks — trenching or ducting under a drive, path or lawn to reach a detached garage or a pedestal.
- An earth rod — needed with some chargers on a PME supply. See PME earthing explained.
- Hard walls — thick stone walls in older properties take longer to drill and make good.
From enquiry to switch-on
The calendar time is usually set by three things. First, the survey: many installers quote from photos of your consumer unit, meter and parking spot within a few days, with a site visit for anything complex. Second, availability: local installers can be booked a week or more ahead, especially in spring when many new cars are delivered. Third, the network operator: for a standard 7kW charger the installer simply notifies them, but if your main fuse is small or your supply is shared with a neighbour (a "looped" supply), an upgrade may be needed first, which can add a few weeks.
If you have a car delivery date, tell us when you ask for a quote. Booking two to three weeks ahead is usually comfortable.
How to speed things up
- Send clear photos of your consumer unit (cover on), your electricity meter and main fuse, and the route to your parking spot.
- Decide roughly where you want the charger before the survey.
- Sort any permissions in advance — landlord, freeholder or council. Our installation checklist covers them.
- Make sure the installer can reach the consumer unit, meter and charger position on the day.